Richmond Terminal Station 

As the owner and operator of the Richmond Terminal Station in Mary Street, we initiated works in 2012 to upgrade this facility.

As part of our ongoing commitment to the safe and reliable supply of electricity, we will be replacing most of the equipment at our Richmond Terminal Station to incorporate the latest technology.

Project Progress

To date significant changes have taken place at the Richmond Terminal Station with two of the three new buildings (220kV switch building and 22kV switch building) now completed including new facades. The construction of the third, the new 66kV building situated near the eastern end of Allan Bain Reserve, is still in progress.

This building will be completed during 2017 with the same façade as the 22kV building.

These new buildings contain the compact Gas Insulated Switchgear. As each building is completed, and the new switchgear installed, we can then remove the old outdoor switchgear. Some demolition of the old switchgear has already occurred and more will be removed as the project progresses.

Out of Hours Works – April 2017

We will be conducting Out of Hours works on the following dates:

  • Saturday 1st April and Sunday 2nd April
  • Saturday 8th April and Sunday 9th April

Works will be conducted between 7am and 5pm on all days.

For further information on the works, please read the notification.

Contact us

Contact us icon

richmondts@ausnetservices.com.au

1300 4636 787 (1800 INFO RTS)

Consultation Manager
Richmond Terminal Station Upgrade
Locked Bag 14051
Melbourne City Mail Centre
Victoria, 8001

RTS 1

The 220kV switch building.

RTS facade

The 22kV switch building.

Landscaping of Mary Street

We have received approval from the City of Yarra to landscape the Mary Street nature strip in front of our site. This involves planting native shrubs from north to south and installing a walking path and pram ramp linking the McConchie and Allan Bain reserves.

Our planting is being undertaken in stages: 

  • Stage 1: planting and path installation to the south of our entrance, which is now complete.
  • Stage 2: planting to the north of our entrance, according to our landscaping schedule.

 

Mary Street landscaping

Progress update

A timeline of project milestones is provided below.

 

Date 

Milestone 

April 2012 

Planning permit granted

Late 2012

Project works commenced

Late 2018

Project works scheduled for completion

Community engagement

For more information about the Richmond Terminal Station upgrade project and our ongoing commitment to the local community, please browse our series of newsletters below.