Glenrowan Solar Farm

Location: 4km south-west of Glenrowan VIC

Construction timeframe: November 2022 to late 2023

Overview

We’ve been engaged by CIMIC Group company, Pacific Partnerships Pty Ltd, to connect the 125 megawatt (MW) Glenrowan Solar Farm to the electricity grid.

We’ll design, build, own and operate the transmission assets for the solar farm.

When complete in late 2023, the Glenrowan Solar Farm will provide enough clean energy to power 45,000 homes each year.

What we’re doing

  • Building a new, 5-kilometre, 33 kilovolt (kV) underground transmission line
  • Upgrading Glenrowan Terminal Station, including a new 120 mega-volt-ampere (MVA) transformer.

Contact us

Get in touch for more information, or if you have any questions:

Phone: 1300 360 795
Email: solarfarms@ausnetservices.com.au